Ivanhoe Mines has achieved three significant development milestones at the Platreef Mine in South Africa, marking important progress in the mine’s phased expansion.
The milestones include the completion of Shaft #3, the commencement of earthworks at the Phase 2 concentrator site, and the start of widening Shaft #2.
Shaft #3 completed
Completed on schedule in late March 2026, Shaft #3 increases the mine’s total hoisting capacity five-fold. Once fully commissioned, it will support the ramp-up of Phase 1 operations and accelerate underground development for Phase 2.
Phase 2 concentrator construction underway
Ground was broken at the Phase 2 concentrator site on April 9, 2026. The new 3.3-million-tonne-per-annum concentrator is targeted for completion in the fourth quarter of 2027. The expansion is expected to increase annualized production to more than 450,000 ounces of platinum, palladium, rhodium and gold.
Shaft #2 widening begins
Work is also underway to widen Shaft #2 from its initial 3.1-metre diameter to its final 10-metre diameter. Once completed, the shaft will provide an additional eight million tonnes per annum of hoisting capacity, supporting Phase 2 operations and the future Phase 3 expansion. It is expected to be ready to hoist labour and materials by the end of 2028, with ore hoisting targeted for the end of 2029.
Together, these milestones represent a major step forward in the development of Platreef, positioning the mine for increased production and further expansion as Ivanhoe Mines advances one of the world’s significant new sources of platinum-group metals.